Leen Alkhair lifts factory contract to SAR 389 million from SAR 294 million

Leen Alkhair raised its factory construction contract with Arsan Al-Oula to SAR 389.2 million from SAR 294.4 million.

· Last verified: 26 Nov 2026 (Saudi Exchange (Tadawul))

Summary

  • Leen Alkhair raised its factory construction contract with Arsan Al-Oula to SAR 389.2 million from SAR 294.4 million.
  • Preliminary handover pushed to September 30, 2027; final handover targeted March 31, 2028.
  • Deal is a related-party transaction: the board chairman holds an indirect interest in the contractor.

The latest

The construction contract for Leen Alkhair Trading Company's new factory has been repriced to SAR 389,159,000 from SAR 294,422,640, excluding VAT, under an addendum signed on November 25, 2026. The company told the Saudi Exchange the increase follows updated engineering plans and designs that changed the scope of work, quantities and technical specifications. Preliminary handover moves to September 30, 2027.

Details

  • The numbers: Leen Alkhair said the contract value with Arsan Al-Oula Contracting Company was adjusted to SAR 389,159,000 from SAR 294,422,640, excluding value-added tax. The company attributed the change to new works and modifications to the project's scope, quantities and technical specifications following revised engineering and operational requirements.
  • The timeline: The contract duration was extended to September 30, 2027 for preliminary handover and trial operation, under a phased plan covering testing of systems, facilities and production lines. March 31, 2028 was set as the target date for final handover, after technical and operational testing and the resolution of any observations on the contracted works.
  • Built-up area: According to the disclosure, the factory is being built on a 20,000-square-meter plot, with total built-up area rising to about 29,000 square meters from roughly 12,960 square meters, an increase of nearly 124%. The facility was redesigned from a single-story structure into a three-story building.
  • Production lines: The number of production and packaging lines rose to 48 from 20, an increase of 140%, the company said. The lines are to cover preparation and packaging of fruits and vegetables, pre-cut produce, ready-to-eat salads, juices, sandwiches, prepared meals, soups, sauces and other value-added food products.
  • Capacity targets: Targeted annual production capacity was raised to more than 500,000 tons under the revised plan, from over 200,000 tons in the initial concept. Targeted daily capacity rose to over 1,000 tons from approximately 550 tons, according to the announcement filed with the Saudi Exchange.
  • Related party: Leen Alkhair said the engagement with Arsan Al-Oula constitutes a transaction with a related party, because Chairman of the Board Saud Mohammed Abdullah Al-Shuraim holds an indirect interest in the contracted entity. The company stated the amendment falls within ordinary business activities and that no preferential treatment was granted.
  • Expected impact: The company expects that, once completed and in commercial operation, the project will improve operational efficiency, increase product value-add, diversify revenue streams, boost production capacity, reduce waste and loss, and strengthen competitiveness. It noted actual results will depend on actual levels of operation, production, sales and costs.
  • Origin of deal: The original contract with Arsan Al-Oula was announced on the Tadawul website on November 1, 2023, covering construction, engineering and operational works for the factory, including procurement and bringing the facility fully into service. The project has since passed through stages of engineering, technical and operational development.

Between the lines

The repricing is proportionally smaller than the physical expansion it funds: the contract value rises about 32%, while built-up area rises nearly 124% and production lines 140%. The company has not tied the added SAR 94.7 million to any single element of the revised scope, listing instead new works, quantity changes and specification revisions together.

What's next

The preliminary handover and trial operation date of September 30, 2027 is the next hard marker, followed by the March 31, 2028 final handover target. Further Tadawul filings would disclose any additional change to scope, value or schedule.

Source: Saudi Exchange (Tadawul)