Al Jouf Agricultural approves SAR 398 million electrification bids
Al Jouf Agricultural Development approved bids worth SAR 398,429,233 to electrify its Basaita facilities.
· Last verified: 12 Nov 2026 (Saudi Exchange (Tadawul))

Summary
- Al Jouf Agricultural Development approved bids worth SAR 398,429,233 to electrify its Basaita facilities.
- The total sits roughly SAR 102 million below the SAR 500 million budget board members set in January.
- The switch removes liquid fuel from the company's largest operating site within 13 months.
The latest
Al Jouf Agricultural Development Company has approved contractor bids worth SAR 398,429,233, excluding value-added tax, to connect electricity to its facilities at Basaita Center in the Al Jouf region under the liquid fuel displacement program. The board signed off by circulation on 11 November 2026 after technical and financial evaluation of the submitted offers, the company told Saudi Exchange.
Details
- The figure: The company put the combined value of the approved bids at SAR 398,429,233, excluding value-added tax, about SAR 102 million under the SAR 500 million estimated budget the board attached to the project when it first approved moving forward in January, according to the disclosure filed with Saudi Exchange.
- The scope: The package covers four work streams: the internal electricity network, external interconnection cable lines, engineering supervision and contract management for the internal network, and the same for the external connection. The company did not name the contractors awarded any of the four components.
- The decision: The board acted by circulation rather than in session, with the resolution dated 11 November 2026. Al Jouf said the approval followed completion of technical and financial evaluation of the offers received and a review of the recommendations issued by the relevant committees.
- The timeline: Execution is set to begin before the end of the fourth quarter of 2026, with the works running 13 months from the start date. On that schedule the electrification would be completed during the first quarter of 2028, though Al Jouf did not publish a target completion date of its own.
- Still open: Al Jouf said it is continuing to study and negotiate the final phase of the project, which was not included in the SAR 398,429,233 approved on 11 November. The company gave no value for that remaining phase and set no deadline for concluding the negotiations.
- Financial impact: The company said the financial impact will be announced once the project is complete, rather than at award or at the start of execution. No figure was given for expected savings from replacing liquid fuel with grid power at the Basaita facilities.
- The program: The project falls under the liquid fuel displacement program, the Saudi push to shift industrial and agricultural consumers off diesel and heavy fuel oil onto the electricity grid. Al Jouf framed the Basaita works as its participation in that program in both disclosures.
- The sequence: The board first approved proceeding with the project on 28 January 2026, corresponding to 9 Shaaban 1447, and disclosed it to the market the following day. The November filing was published as a development update on that earlier announcement, with the delay section marked not applicable.
Background
Basaita Center in Al Jouf hosts Al Jouf Agricultural Development's production facilities in the kingdom's northern agricultural belt, where irrigation and processing equipment has run on liquid fuel. The January board decision set the SAR 500 million estimate that the November bid approval now undercuts.
Between the lines
The gap between the SAR 500 million estimate and the SAR 398,429,233 in approved bids is not a final cost figure: the company says the last phase is still under negotiation and unpriced. Al Jouf has also deferred any statement on financial impact until completion, leaving the economics of the fuel switch undisclosed until at least 2028 on its own 13-month schedule.
What's next
Watch for the start of execution before the end of the fourth quarter of 2026, the award terms for the final phase still under negotiation, and any Saudi Exchange filing naming the contractors or updating the project's cost.
Source: Saudi Exchange (Tadawul)