Arabian Drilling signs SAR 1.5 billion Khafji rig contract
Arabian Drilling won a SAR 1.5 billion contract from Khafji Joint Operations for two self-propelled service platforms.

· Last verified: 22 Nov 2026 (Saudi Exchange (Tadawul) — Arabian Drilling disclosure)

Summary
- Arabian Drilling won a SAR 1.5 billion contract from Khafji Joint Operations for two self-propelled service platforms.
- Terms run 10 years for the first platform and 15 years for the second.
- The deal replaces an existing two-platform contract, locking in Khafji revenue into the 2040s.
The latest
Arabian Drilling has signed a SAR 1.5 billion long-term contract with Khafji Joint Operations to supply and operate two self-propelled offshore service platforms, according to the company's disclosure to the Saudi Exchange. The agreement replaces an existing contract covering two platforms already in service. The first unit carries a 10-year term, the second 15 years.
Details
- The value: The company put the contract at SAR 1.5 billion, covering the provision and operation of two self-propelled offshore service platforms for Khafji Joint Operations. The disclosure did not break the figure down between the two units or specify day rates.
- The counterparty: Khafji Joint Operations is the contracting entity. Arabian Drilling stated there are no related parties involved in the agreement, meaning the award falls outside related-party transaction disclosure requirements.
- The terms: The first platform is contracted for 10 years, the second for 15 years. Both terms run from each unit's own start of operations rather than from signing, extending Arabian Drilling's revenue visibility at Khafji well beyond the current decade.
- Replacement, not addition: The company said the new agreement replaces an existing contract for two offshore service platforms already working for Khafji. That framing matters for modelling: part of the SAR 1.5 billion substitutes for revenue the company was already booking rather than adding entirely new work.
- The dates: Arabian Drilling said the award was announced and the contract signed on 19 November 2026, corresponding to 9 Jumada al-Akhirah 1448. The disclosure was filed with the Saudi Exchange on 22 November 2026 at 08:03.
- Financial impact: The company expects the contract to strengthen its financial results from the start of operations of each platform — the fourth quarter of 2026 for the first unit and the fourth quarter of 2028 for the second. No earnings estimate was attached to either phase.
- The two-year gap: The staggered start dates mean roughly two years separate the two revenue streams, with the second platform's contribution not landing until late 2028. Arabian Drilling did not disclose whether capital spending is required ahead of that second start-up.
- The share reaction: Arabian Drilling, listed under code 2381 on the Saudi Exchange, was quoted down 2.40% alongside the disclosure.
Background
Khafji Joint Operations runs production in the Partitioned Neutral Zone shared by Saudi Arabia and Kuwait. Offshore service platforms there support drilling, workover and maintenance activity, and are typically contracted on multi-year terms that tie a contractor's fleet to a single field for the full duration.
Between the lines
The structure of the award is as notable as its size. Because the contract supersedes an existing two-platform deal rather than sitting alongside it, the headline SAR 1.5 billion overstates the incremental revenue. What the company gains is duration: terms of 10 and 15 years convert work already in hand into contracted backlog stretching toward 2041 for the second unit, a form of visibility the market usually values more than a single year's uplift.
What's next
The first platform's start-up in the fourth quarter of 2026 is the near-term marker, with any contribution showing in the company's Q4 results. The second unit's late-2028 start is the next scheduled trigger.