Saipem wins $650 million in Aramco offshore contracts in Saudi Arabia
Saipem said it won two offshore contracts worth roughly $650 million from Aramco in Saudi Arabia.

· Last verified: 27 Nov 2026 (Saipem)

Summary
- Saipem said it won two offshore contracts worth roughly $650 million from Aramco in Saudi Arabia.
- The awards fall under Saipem's existing Long-Term Agreement with Aramco, covering seven production deck manifolds.
- Fabrication runs at Saipem's Saudi yard, keeping Aramco's offshore field spending and local supply chains active.
The latest
Two offshore contracts worth approximately $650 million have been awarded to Saipem by Aramco in Saudi Arabia, the Italian contractor announced on November 25. Both are Contract Release Purchase Orders issued under Saipem's existing Long-Term Agreement with the Saudi producer, and together they cover engineering, procurement, construction and installation work across five offshore fields.
Details
- The headline figure: Saipem put the approximate combined value of the two awards at $650 million, stated in the release headline. The company said the amount covers engineering, procurement, construction, installation, pipeline and power cable scope across both contracts, without breaking the total down between them.
- The contracting vehicle: Both awards are Contract Release Purchase Orders, known as CRPOs, issued under Saipem's existing Long-Term Agreement with Aramco rather than as standalone tenders. The structure lets Aramco release defined work packages to the contractor without reopening competition.
- First contract scope: CRPO 168 covers EPCI work on four production deck manifolds, roughly 14 km of pipeline in 12 to 16 inch diameters, and about 24 km of 15 kV cables, plus associated subsea facilities serving the Abu Safah, Safaniyah, Manifa and Berri fields.
- Onshore element: The first contract also includes onshore activities for the tie-in at the drill site in the Manifa field, according to Saipem, extending the package beyond purely offshore installation work.
- Second contract scope: CRPO 170 covers EPCI activities for three production deck manifolds, approximately 25 km of pipeline in 12 to 16 inch diameters and around 17 km of 15 kV cables, together with associated subsea facilities at the Marjan field.
- The fields: Across the two awards, the work touches Abu Safah, Safaniyah, Manifa, Berri and Marjan — five of Aramco's offshore developments. Saipem did not disclose a completion schedule or delivery dates for either contract.
- Execution plan: Saipem said offshore operations will use construction vessels already deployed in the region, avoiding new mobilisation. Fabrication will be carried out at the company's Saudi Fabrication Yard by Saipem Taqa Al-Rushaid Fabricators Co. Ltd., which Saipem said contributes to developing local industry capabilities.
- The company framing: Saipem described the awards as consolidating its presence in Saudi Arabia and its longstanding relationship with Aramco, and as reflecting what it called advanced engineering capabilities in project execution. The statement was issued from Milan.
- Combined volumes: Taken together, the two orders cover seven production deck manifolds, roughly 39 km of pipeline and about 41 km of 15 kV cable, based on the individual figures Saipem published for each contract.
Background
Contract Release Purchase Orders are issued under an existing Long-Term Agreement, a framework that lets Aramco award successive work packages to a pre-qualified contractor. Saipem's Saudi fabrication work is executed through Saipem Taqa Al-Rushaid Fabricators Co. Ltd. at the company's yard in the Kingdom.
Between the lines
The pattern in the award is continuity rather than expansion: vessels already in the region, a yard already operating in the Kingdom, and a contracting vehicle already in place. That combination suggests Aramco is releasing work into an established pipeline, and keeps spending flowing to local fabrication capacity through the Saudi yard Saipem names in its statement.
What's next
Watch for the start of fabrication at Saipem's Saudi yard, any schedule or delivery dates the company later discloses, and whether further CRPOs are released under the same Long-Term Agreement with Aramco.
Source: Saipem