Economy

Anmat signs SAR 129.9 million contract to rehabilitate HRDF Riyadh headquarters

Anmat Technology Trading signed a SAR 129.9 million rehabilitation contract with the Human Resources Development Fund.

· Last verified: 26 Nov 2026 (Saudi Exchange (Tadawul))

Summary

  • Anmat Technology Trading signed a SAR 129.9 million rehabilitation contract with the Human Resources Development Fund.
  • The 13-month project covers the fund's Riyadh headquarters, with work starting from the commencement report date.
  • Anmat expects the contract's financial impact to appear in its 2027 results.

The latest

A SAR 129,919,773.40 contract, inclusive of value added tax, will see Anmat Technology Trading Company carry out rehabilitation works on the Riyadh headquarters of the Human Resources Development Fund. The company said the agreement was signed on 24 November 2026 and runs for 13 months from the date of the work commencement report. Anmat expects the earnings impact in fiscal year 2027.

Details

  • The value: Anmat put the contract at SAR 129,919,773.40 including value added tax, in a disclosure filed to the Saudi Exchange. The company did not break out the VAT component or state the contract value excluding tax, nor did it disclose expected margins on the work.
  • The counterparty: The client is the Human Resources Development Fund, known as Hadaf, the Saudi government fund whose Riyadh headquarters is the subject of the works. Anmat said no related parties are involved in the agreement.
  • The scope: The project covers execution of rehabilitation works for the fund's headquarters in Riyadh, carried out in line with the approved terms and specifications, according to the company's announcement. Anmat did not itemise the individual works or name any subcontractors.
  • The timeline: The contract runs 13 months, counted from the date of the work commencement report rather than from signing. The company did not disclose when that commencement report is expected to be issued, leaving the completion date undefined in the filing.
  • Award versus signing: Anmat said the award was announced on 1 October 2026, corresponding to 20 Rabi al-Thani 1448, with the contract itself signed on 24 November 2026, corresponding to 14 Jumada al-Thani 1448 — a gap of close to eight weeks between award and signature.
  • The accounting: The company said the financial impact of the contract is expected to be reflected in its results during fiscal year 2027. That points past the current financial year, consistent with a 13-month build whose revenue recognition follows execution rather than signature.
  • The disclosure: The announcement was filed through the Saudi Exchange issuer announcements channel on 25 November 2026 at 08:19:50, the standard route for listed Saudi companies reporting material contracts.

Between the lines

Two dates in the filing set expectations. Because the 13-month clock starts from the work commencement report, not the 24 November signing, the project's end point is not yet fixed by the disclosure. That is consistent with the company steering the earnings impact to 2027 rather than booking it earlier.

What's next

Watch for the issuance of the work commencement report, which starts the 13-month clock, and for any further Tadawul disclosure from Anmat specifying margins, scope changes or the project's expected completion date.

Source: Saudi Exchange (Tadawul)