United Arab Emirates · Data centre · Under construction · Ajman · Expected Initial phase Dec 2026 · Khazna Data Centers (G42)

Khazna's 100 MW AI-optimised data centre in Ajman, which Khazna says will be the region's first; with the steel structures complete, the initial project phase is due for completion in December 2026.

khaznadatacenters.com ↗

Verified · updated 1 Oct 2026

Key facts

100 MW

Announced capacity

Khazna Data Centers·as stated Apr 2025·21 Apr 2025·About this indicator