DAMAC targets 10GW data-centre capacity by end-2027, Sajwani says

DAMAC plans to lift planned global data-centre capacity to 10GW by end-2027, from roughly 6GW.

· Source: Bloomberg · Last verified: 14 Nov 2026

Summary

  • DAMAC plans to lift planned global data-centre capacity to 10GW by end-2027, from roughly 6GW.
  • The group has already deployed about $9 billion of a $20 billion US data-centre programme.
  • Sajwani said construction costs have risen 30%, with a further 20-30% increase possible.

The latest

DAMAC Group intends to raise the planned capacity of its global data-centre portfolio to 10GW by the end of 2027, up from around 6GW currently planned, founder and chairman Hussain Sajwani said at Bloomberg Invest Dubai 2026. He tied the expansion to accelerating demand for artificial intelligence and cloud-computing infrastructure, and said development costs have already climbed about 30%.

Details

  • The current portfolio: Sajwani said DAMAC Digital's pipeline stands at roughly 6,000MW across 14 countries, split between about 1,000MW in the United States, 2,500MW in Europe and 2,500MW in Asia. Reaching 10GW would require adding close to two-thirds again on top of what is currently planned.
  • The US programme: Sajwani reaffirmed DAMAC's previously announced $20 billion US data-centre investment programme, saying around $9 billion has already been invested. He said the remainder would proceed in line with the availability of suitable land and electrical power, without setting a completion date.
  • Where it expands next: Planned expansion covers Thailand, Malaysia, the Philippines, Finland, Spain, Greece, Italy, Turkiye and the United States, with other markets under assessment. Sajwani said the group intends to acquire additional land outside the United States over the next 12 to 18 months.
  • Australia and Britain: Sajwani said DAMAC is in serious negotiations to acquire a large site in Australia and is also seeking to expand in the United Kingdom. He did not name the Australian site, disclose a purchase value, or say when either transaction might be concluded.
  • The build specification: The group is concentrating on large facilities starting at around 100MW and relying primarily on liquid-cooling technologies, Sajwani said, designed to support AI chips and high-density computing. That threshold places the projects in the hyperscale tier rather than the smaller enterprise sites common in most regional markets.
  • The cost pressure: Data-centre development costs have risen by around 30%, Sajwani said, and could increase by a further 20 to 30%. He identified the United States and Europe as among the most expensive markets to build in, while Asian markets offer advantages in labour and equipment costs.
  • The technology bets: Sajwani said his investments in artificial intelligence and technology companies have generated substantial returns, with holdings in OpenAI, SpaceX and Anthropic alone producing gains running into billions of dollars. He did not disclose the size of the individual stakes or when they were acquired.
  • The Anthropic comparison: His Anthropic investment, made less than two years ago, had generated gains comparable to those accumulated across roughly three decades of his previous business activity, Sajwani said, presenting it as a measure of how quickly opportunity is shifting toward technology.

Background

DAMAC Group, founded by Sajwani, built its name in Gulf property development before moving into digital infrastructure through DAMAC Digital. Its data-centre push places it among the UAE investors channelling capital into the global buildout of computing capacity for artificial intelligence.

Between the lines

The two figures Sajwani gave sit in tension: he is targeting a capacity increase of roughly two-thirds within about a year while conceding costs have already risen 30% and may rise another 20-30%. Tying the remaining US spending to land and power availability rather than to a date suggests the binding constraint is physical supply rather than capital. His stated preference for Asian labour and equipment costs points the same way.

What's next

Watch for confirmation of the Australian site acquisition, any announced UK entry, and whether DAMAC discloses land purchases outside the United States within the 12 to 18-month window Sajwani set.