Money and business in the Middle East.

AI

Saudi fund, Humain sign $667 million AI data centre financing

Saudi Arabia's National Infrastructure Fund and Humain signed two facilities worth 2.5 billion riyals.

· Last verified: 9 Nov 2026 (Argaam, citing the Saudi Press Agency (SPA))

Summary

  • Saudi Arabia's National Infrastructure Fund and Humain signed two facilities worth 2.5 billion riyals.
  • The deals are the first under the fund's AI data centre financing programme.
  • Power infrastructure is being built to carry data centre loads reaching 1 gigawatt.

The latest

Two financing facilities worth a combined 2.5 billion riyals, or $667 million, were signed by Saudi Arabia's National Infrastructure Fund and Humain to fund artificial intelligence computing capacity and the power infrastructure behind it, according to the Saudi Press Agency. The agreements are the first transactions executed under the fund's AI data centre financing programme.

Details

  • The GPU facility: The first facility, worth up to 1.1 billion riyals or $293.3 million, is dedicated to financing graphics processing units, according to the Saudi Press Agency. It supports the purchase and supply of GPUs with an IT load capacity of roughly 25 megawatts, the core computing hardware used to train and run AI models.
  • The power facility: The second facility, worth up to 1.4 billion riyals or $373.3 million, funds the critical energy infrastructure needed for Humain's AI data centres in the kingdom. It covers transformer substations, power transmission infrastructure and the connection facilities linking the sites to the national electricity grid.
  • Built for 1 gigawatt: The energy infrastructure has been designed to accommodate future data centre expansion with IT loads reaching 1 gigawatt, according to the Saudi Press Agency, a scale far beyond the 25 megawatts of GPU capacity covered by the first facility in this round.
  • The investor pitch: The stated purpose of designing for that headroom is to create an environment that attracts data centre developers, hyperscale computing operators and institutional investors. The agreements do not name any such developers or investors as having committed to the sites.
  • Davos origin: The two facilities represent the first phase of a strategic framework financing agreement announced by the fund and Humain at Davos in January 2026. That framework set out non-binding financing terms of up to 4.5 billion riyals, equivalent to $1.2 billion.
  • What remains unused: With 2.5 billion riyals now committed, roughly 2 billion riyals of the Davos framework remains undrawn. The framework's stated purpose is supporting artificial intelligence projects and digital infrastructure across the kingdom.
  • Programme debut: The two agreements are the inaugural deals under the National Infrastructure Fund's AI data centre financing programme, a dedicated lending track for compute and the power systems that run it. No timeline was announced for deployment of the GPUs or completion of the grid connection works.

Between the lines

The split between the two facilities is the signal: more money is going into substations, transmission and grid connections than into the chips themselves. Building power capacity for 1 gigawatt while financing 25 megawatts of GPUs points to infrastructure laid ahead of demand, with the stated aim of drawing in hyperscale operators and institutional capital later.

What's next

Watch whether the remaining roughly 2 billion riyals of the Davos framework is converted into binding facilities, and whether any hyperscale operator or institutional investor is named as taking capacity at the sites.

Source: Argaam, citing the Saudi Press Agency (SPA)