Bahrain nearly doubles North Sitra sewage plant capacity to 30,000 cubic metres
North Sitra treatment plant capacity rises to 30,000 cubic metres daily, up from 16,500 in 2009.

· Last verified: 26 Nov 2026 (Bahrain News Agency (BNA))

Summary
- North Sitra treatment plant capacity rises to 30,000 cubic metres daily, up from 16,500 in 2009.
- Expansion cost roughly BD15.5 million and was implemented by Blue Water Bio using HYBACS technology.
- Around 13,000 properties are expected to benefit, with treated water directed toward irrigation and afforestation.
The latest
The North Sitra Sewage Treatment Plant can now process 30,000 cubic metres of wastewater a day, up from 16,500, after an expansion inaugurated Thursday by Deputy Prime Minister Shaikh Khalid bin Abdullah Al Khalifa. Works Minister Ibrahim bin Hassan Al Hawaj said the upgrade cost approximately BD15.5 million. It is the plant's second expansion since it opened in 1985.
Details
- The numbers: Al Hawaj said the plant started in 1985 with a capacity of 7,000 cubic metres per day. A first expansion in 2009 lifted that to 16,500, and the latest works raise it to 30,000 cubic metres per day — more than four times the original design capacity.
- The contractor: The expansion was implemented by Blue Water Bio at a cost of approximately BD15.5 million using HYBACS technology, according to Al Hawaj, who said it would improve treatment efficiency, raise operational capacity and produce treated water meeting approved specifications and design standards.
- Who it serves: The plant covers the entire island of Sitra, including the North Sitra Industrial Area, as well as East Sitra and Nabih Saleh islands. Following the expansion, roughly 13,000 properties are expected to benefit from its services, the Works Minister said.
- The demand driver: Al Hawaj tied the new capacity to two pressures: housing projects in East Sitra City and industrial growth in North Sitra. The upgrade is intended to absorb both, rather than simply replace ageing equipment at a plant operating for more than four decades.
- Government programme: Shaikh Khalid bin Abdullah said the project falls within the priorities of the Government Programme (2023–2026), which includes developing sewage systems to meet urban development requirements. He described the second expansion as evidence of continued development planning for existing facilities.
- Water reuse: The Deputy Prime Minister pointed to the strategic weight of the wastewater sector in supporting urban and economic growth, protecting the environment and public health, and strengthening water security through the reuse of treated water.
- Afforestation link: Al Hawaj said the project is part of the Works Ministry's strategic plan to develop the treated water system and widen its use for irrigation, particularly in afforestation projects and expanding green spaces, supporting Bahrain's plan to double the number of trees in the Kingdom by 2035.
- Not specified: Neither official disclosed how much of the plant's treated output is currently routed to irrigation, nor a timeline for reaching the expanded capacity in full operation.
Background
The North Sitra plant has operated since 1985 and has now been expanded twice — in 2009 and again with the works inaugurated this week. The Government Programme covering 2023–2026 lists sewage system development among its stated priorities for urban growth.
Between the lines
The framing from both officials points beyond sanitation. Capacity was sized against named growth sources — East Sitra housing and North Sitra industry — rather than current load, and the treated output is being positioned as an irrigation input for the 2035 tree-doubling target. That makes the plant a supply asset in Bahrain's water balance, not only a disposal facility.
What's next
Watch for the volume of treated water actually allocated to irrigation and afforestation projects, and whether remaining Government Programme sewage commitments are delivered before the plan period closes at the end of 2026.
Source: Bahrain News Agency (BNA)